Every project follows some process, either planned or accidental. A process framework names the activities that every project needs, and the process models arrange them in different ways.

The Generic Process Framework

A software process is a set of activities that leads to a software product. The generic framework has five framework activities. Communication gathers requirements from the customer. Planning estimates the work, schedule and risks. Modeling builds models of the requirements and the design. Construction produces the code and tests it. Deployment delivers the software to the customer for evaluation and feedback. Umbrella activities such as project tracking, risk management, quality assurance, reviews, configuration management and documentation continue through the whole project.

Definition: Software process. A set of related activities, actions and tasks that are performed to build a software product.

The Waterfall Model

The waterfall model, also called the classic life cycle, arranges the activities in a linear sequence, and each phase starts when the previous one is finished. The phases are requirements analysis, design, implementation and coding, testing, deployment and maintenance. The output of each phase is a document that is the input of the next. It is simple, easy to manage and suits projects whose requirements are well understood and stable, such as a small well-defined system.

Strengths and Weaknesses

The waterfall model has clear milestones and strong documentation. Its weakness is that real projects rarely follow a sequence without change. Customers find it hard to state all requirements at the start. A working version appears only late in the project, so a serious error found at that time is costly. Because feedback comes late, it is a poor choice when requirements are likely to change.

Variations of the waterfall model exist. The V-model shows that each development phase has a matching test phase, so requirements are checked by acceptance tests and the design is checked by integration tests. The model was widely used in government and defence projects, where fixed contracts and detailed documents are required. In modern practice a pure waterfall process is rare for large products, but its discipline of writing requirements and design down before coding is still valued in regulated industries such as medical devices and aviation.

Table 1.2: Phases of the waterfall model

Phase Activity Output
Requirements Collect and analyse needs Requirements document
Design Plan structure of the system Design document
Implementation Write the code Source code
Testing Check against requirements Test report
Maintenance Correct and improve Updated software

Example 1.2: Choosing waterfall

Problem: A college asks for a fixed-format attendance report generator whose rules are written in an official circular. Is the waterfall model suitable?

Solution:

  1. The requirements are fixed by the circular and are unlikely to change.
  2. The system is small, so a sequential plan is easy to follow.

Result: Yes, the waterfall model is suitable because the requirements are stable and well understood.

Common mistakes

  • Thinking that the waterfall model allows easy return to earlier phases.
  • Forgetting that umbrella activities run through all phases.
  • Using the model for projects whose requirements are unclear.

Key takeaways

  • The five framework activities are communication, planning, modeling, construction and deployment.
  • Umbrella activities continue throughout the project.
  • Waterfall is linear, with each phase producing a document.
  • Waterfall suits stable, well-understood requirements.

Practice questions

  1. List the generic framework activities.
  2. Give one weakness of the waterfall model.
  3. What are umbrella activities?

Answers to the practice questions

  1. Communication, planning, modeling, construction and deployment.
  2. A working version appears late, so errors are found late and are costly.
  3. Activities such as risk management and quality assurance that continue through the whole project.