After the risks are ranked, a plan is needed for what to do about each. The RMMM approach provides it.

The Three Parts

Mitigation means to reduce the probability or the impact of the risk before it occurs. Monitoring means to watch the project for signs that the risk is becoming real. Management means the contingency plan, the actions to take when the risk does happen. Together they are called RMMM.

Definition: RMMM. The set of activities of risk mitigation, monitoring and management used to deal with each important risk.

Example: High Staff Turnover

Suppose that the risk is that experienced staff may leave. Mitigation includes meeting staff to find the causes, improving working conditions, and documenting the work so that others can take over. Monitoring includes watching the attitude of team members, the morale of the group and the relations among people, and the availability of jobs elsewhere. Management includes a backup person for every critical task, quick handover of the work, and extra time for the new person to learn.

The RMMM Plan

The RMMM plan documents all this. It lists each risk with its probability, impact and exposure, and the mitigation, monitoring and management steps with the person responsible. A simpler alternative is the risk information sheet (RIS), a one-page form for each risk, which records its description, refinement, probability, impact, and the three steps. The plan is reviewed regularly, since risks change as the project advances, and a mitigation step has a cost that must be weighed against the risk exposure.

Risks are linked to the timing of the project. Early in the project, risks arise mostly from unclear requirements and new technology, while later the risks are related to testing, integration and delivery. The risk table, which lists each risk with its category, probability and impact, is sorted by exposure, and a cut-off line is drawn. Risks above the line are given plans, and those below are watched. Some risks, such as the loss of a key person, are common to nearly all projects, and a list of such risks from earlier projects is a valuable asset for the organisation. The plan is not static, and each review may add, remove or re-rank risks.

Table 2.5: RMMM for staff turnover

Part Purpose Action
Mitigation Reduce probability or impact Document work, improve conditions
Monitoring Watch for signs of the risk Track team morale and absences
Management Respond if it occurs Backup person, quick handover

Example 2.5: Choosing mitigation or contingency

Problem: A risk of a late hardware delivery has exposure of 40000 rupees. Ordering early from a second supplier costs 10000 rupees and removes the risk. Is the mitigation worthwhile?

Solution:

  1. Cost of mitigation is 10000 rupees.
  2. Exposure removed is 40000 rupees.

Result: The mitigation is worthwhile, because its cost of 10000 is lower than the exposure of 40000.

Common mistakes

  • Confusing mitigation, which is done before the risk, with management, which is done after it occurs.
  • Writing a plan and not assigning a person to each action.
  • Spending on mitigation that costs more than the exposure it removes.

Key takeaways

  • RMMM stands for mitigation, monitoring and management.
  • Mitigation acts before, monitoring watches, management responds when the risk occurs.
  • A risk information sheet records the plan for one risk.
  • The cost of mitigation should be less than the risk exposure.

Practice questions

  1. What does RMMM stand for?
  2. What is mitigation?
  3. What is a contingency plan?

Answers to the practice questions

  1. Risk mitigation, monitoring and management.
  2. Action taken before a risk occurs to reduce its probability or impact.
  3. The actions to take when a risk becomes a real problem (risk management).